| 6.0 |
COMMISSION'S
OBSERVATION AND ANALYSIS OF LICENSEE'S PROPOSAL
On detailed scrutiny and examination of the RST application
for the FY 2001-02 and the revenue requirement application
for the FY 2002-03 along with clarifications submitted by
the licensee before the Commission, the written and oral
submissions of the objectors and the views of the Members
of the Commission Advisory Committee, the Commission has
passed the order, as detailed below. |
| 6.1 |
Scenario of the Power Sector
Reform in Orissa |
| 6.1.1 |
All the distribution
licensees have made a strong plea that the sectoral survival
is possible in the present Orissa situation only when the
input cost of power purchase is brought down by reducing
the bulk supply tariff charged by GRIDCO to the DISTCOs.
|
| 6.1.2 |
The State of Orissa
was the first to initiate power reform in the country. The
Orissa Electricity Reform Act, 1995 was put into the statute
with a view to restructure the electricity industry in the
state and rationalize the generation, transmission, distribution
and supply of electricity and to create avenues for participation
of private sector entrepreneurs and create infrastructure
for development and management of electricity industry in
an efficient, economic and competitive manner. Orissa Electricity
Regulatory Commission has been constituted under the Act
for overseeing and regulating the affairs of electricity
industry in the State including rationalisation/setting
of tariff. |
| 6.2 |
Restructuring of the Power
Sector |
| 6.2.1 |
Prior to coming into
force of the OER Act, 1995 on 01.4.96, the Thermal Station
at Talcher of 460 MW capacity owned by OSEB was sold to
NTPC in June, 1995 at a consideration of Rs.356.00 Crore. |
| 6.2.2 |
The OSEB was dissolved
and unbundled with the take over of hydro stations owned
by the OSEB and the Government by the Orissa Hydro Power
Corporation and its transmission and distribution business
was taken over by GRIDCO with effect from 1st April 1996.Thereafter,
the distribution and retail supply of electricity was vested
in four distribution companies initially as wholly owned
subsidiary companies of GRIDCO. Three of these distribution
companies were privatised on 1st April 1999 and the fourth
one on 1st September 1999 after disinvestment of its 51%
share. The state owned Orissa Power Generation Corporation
created in 1984 continued to operate as a separate entity
and managed the Ib Thermal Power Station of capacity 420
MW near Jharsuguda. |
| 6.2.3 |
The assets of the erstwhile
OSEB including those of the hydro generating stations were
taken over by the State Government, revalued and transferred
to GRIDCO and OHPC. The upvalued amount was adjusted in
favour of the state Government through grant of equity share
and issue of bonds bearing no interest with a moratorium
period of five years with provision of subsequent conversion
in phases into equity and issue of debentures bearing interest.
Revaluation of assets was considered to enable the Government
of Orissa to realize more realistic value for its past investment
at the time of privatization and also enhance the creditworthiness
of the utilities. The revaluation was based on the revenue
earning potential and was intended as a means of raising
revenue through higher level of depreciation, higher operation
and maintenance cost, higher return on equity for smooth
functioning of the power sector. To sum up the revaluation
was also done with the objective of eliminating GRIDCO's
and OHPC's dependence on budgetary support from Government
of Orissa. |
| 6.2.4 |
The process of reform
and restructuring paved the way for commitment of World
Bank loan of 350 US million dollars for long term capital
investment in the power sector in Orissa along with 65 million
sterling pound funding from the DFID to meet urgent needs
of repair & maintenance expenses and consultancy support.
The World Bank also prepared a report known at the Staff
Appraisal Report in April 1996 on the Orissa Power Sector
Restructuring Project and made financial projections based
on certain assumptions of power purchase, power sale, level
of transmission and distribution loss, collection efficiency
and operating expenses which envisaged that GRIDCO after
meeting all costs will turn around from FY 1997-98 onwards.
There was no provision of transitional support whatsoever
during this period. On the contrary, State Government adjusted
a sum of Rs.340.2 Crore payable to GRIDCO against the upvaluation.
All the liabilities of erstwhile OSEB were also passed on
to GRIDCO based on the above financial analysis and projections. |
| 6.2.5 |
In reality, the projections
did not materialize as envisaged the financial health of
GRIDCO is far from satisfactory as the accumulated losses
of GRIDCO has increased to Rs.1197 Crore by the year FY
1998-99 and is likely to be upto Rs.1378 Crore by 2001-02.
It faces acute liquidity problem as the DISTCOs have paid
to GRIDCO towards purchase of power only about 65.21% of
BST bills upto FY 2001 and 46.42% upto December 2001. |
| 6.2.6 |
However, in the post-reform
period from 1 April, 1996 to 31 March, 2001, the state generators,
namely, OPGC and OHPC have earned profit of Rs.768 Crore
in books which should have made them financially viable
but in reality, OHPC is faced with cash crunch due to non-payment
of its energy dues by GRIDCO. |
| 6.2.7 |
Private capital has
been infused in the form of disinvestment of 49% of equity
shares of OPGC (Rs.603 Crore), sale of 51% share of distribution
business of GRIDCO (Rs.159 Crore). |
| 6.2.8 |
In OSEB days, the State
Government was required to provide necessary subvention
under Section 59 of the Supply Act 1948 so as to leave a
surplus of not less than 3% to OSEB after meeting all expenses
properly chargeable to revenue including O&M and management
expenses, taxes, depreciation and interest etc. for sustenance
of the power sector to meet its socio-economic obligations
of giving power supply to the vulnerable sections of the
society but in the post-reform era, the Government of Orissa
has totally pested itself from the burden of such payment
which on a rough estimate would have come to Rs.2770 Crore
had the OSEB continued as an entity. |
| 6.2.9 |
The Commission reiterates
its observation made in the order dt.19.01.2001 that payment
of subsidies are not in consonance with the spirit of the
Reform Act, 1995 but the State Government's financial back-up
in the form of subvention or subsidy during the transitional
period could have substantially eased the situation as has
been realised and is being implemented in many reforming
States like Andhra Pradesh (Rs.1585 crore), Gujarat (Rs.1260
crore), Uttar Pradesh (Rs.790 crore), Haryana (Rs.769.3
crore for one year) and Rajasthan (Rs.3496.6 crore in four
years), Delhi (@ Rs.500 crore per annum for five years).
This was necessary because the social policies, such as,
Rural Electrification, Lift Irrigation, Kutir Jyoti carried
out at the behest of the State as a matter of state policy
for the benefit of a larger section of the state's population
was continued in the post-reform period and also tariff
can not be made cost reflective in one go, as it would generate
a price shock to consumers. |
| 6.2.10 |
The single most important
factor that raised the revenue requirement of all the licensees
in the post-reform era was the substantial rise in the cost
of hydro power as well as in the cost of transmission and
distribution on account of revaluation of assets as on 01.4.96
and also providing an accelerated rate of depreciation.
Further, in the pre-reform era, power requirement of the
state was met mostly from sources within the State and limited
procurement from Central Generating Stations and CPPs. However,
with the passage of time, the State became more dependent
on drawal of power from the Central Generating Station due
to delayed commissioning of the Upper Indravati Hydro Electric
Project. The NTPC power remained costlier as their power
stations in the eastern regions were new stations and continued
to operate at low PLF accentuating the fixed cost per unit.
On the revenue side, the single most important factor has
been the lack of growth in EHT and HT loads as envisaged. |
| 6.2.11 |
The forecast of consistent
reduction in transmission and distribution loss from an
estimated level of 39.5% for the FY 1996-97 to 22.7% by
the FY 2000-01 has not worked out. Even the initial assessment
of loss as 39.5% for the FY 1996-97 turned out to be 49.4%
as revealed from the audit report during the corresponding
year. |
| 6.2.12 |
The transmission and
distribution sector continued to bear further financial
liabilities due to interest burden on account of debt servicing
of past loans & liabilities and large scale investment
in transmission and distribution for improvement of quality
of power supply without corresponding rise in sale of power. |
| 6.2.13 |
The anticipation that
the impact of revaluation of assets would be offset with
the growth of EHT and HT loads has not worked as the expected
load growth like installation of steel plant at Gopalpur,
Duburi projected in pre-1996 era did not materialize coupled
with recession in the industrial sector severely hurting
the anticipated growth at HT & EHT. Further, to make
the matters worse, the loads in the subsidised categories
have increased. This has adversely affected the revenues
of the utilities. |
| 6.2.14 |
The actual sale of 2760
MU to the industrial HT & EHT bulk supply and railway
in 2000-01 was far below the load projection of 7009 MU
for these categories made in the Staff Appraisal Report
which has seriously affected the revenue earning potential
of the licensees, widened the gap between the cost of supply
and revenue realisation and reduced the scope of cross-subsidy
to low voltage classes of consumers. |
| 6.2.15 |
Had the load projection
contemplated in the Staff Appraisal Report materialized,
the revenue position of the utilities would have been much
better and it would have contributed to an overall reduction
in T&D loss figure. |
| 6.2.16 |
Some HT/EHT consumers
preferred generation of power from their own Captive Power
Plants rather than avail power from DISTCOs on cost consideration
though the Eastern Zone continues to be surplus in generation. |
| 6.2.17 |
Though collection efficiency
is around 98% to 99% in privately managed utilities like
CESC, Calcutta and BSES. Bombay, the DISTCOs in Orissa have
achieved only 75% for 1999-00 and 76% for the year 2000-01.
Their failure to collect the revenue at the tariff permitted
by the Commission from year to year and to convert the lost
units by regularizing unauthorized connection and reducing
load have magnified the liquidity problem. |
| 6.2.18 |
The affordability of
a large section of consumers mostly from domestic, irrigation,
small industrial segments, etc. constituting more than 90%
of the total consumers strength happened to be the weakest
link in attaining a cost based tariff structure, which in
effect would result in reduction of Industrial Tariff and
substantial increase in LT Tariff. |
| 6.2.19 |
It was expected that
a vibrant industrial sector would support and make the power
sector self-sustaining for which no provision was kept to
provide financial support to GRIDCO during the transition
year though GRIDCO in its new incarnation was still required
to undertake socially purposive but unremunerative measures
such as Rural Electrification and supply to the rural poor.
The state's economy had received tremendous setback due
to occurrence of natural calamities like super cyclone,
drought and flood in succession affecting both the utilities
and the consumers. Besides, the customer care of the distribution
companies has left much to be desired raising questions
on efficacy of privatisation. |
| 6.2.20 |
It may be reiterated
that the asset revaluation, absence of subvention from the
Government, high level of transmission and distribution
loss, non-maturing of HT & EHT loads, coupled with poor
billing and collection of the distribution companies are
the causes of imbalancing factors leading to the losses
in the GRIDCO and distribution utilities. |
| 6.2.21 |
Therefore, it is felt
that a mid course correction of the Power Sector Reform
in Orissa is urgently necessary to strengthen the power
sector in the interest of the consumers, investors and the
state's economy. |
| 6.2.22 |
From 01.04.2001 onwards,
the moratorium period of five years allowed on the zero
coupon bond issued to GRIDCO as well as the convertible
bonds issued to OHPC was to expire by 31 March 2001 and
its treatment like conversion of bond to equity and collection
of interest on the balance portion of bond in accordance
with the Government Notification, and realization of interest
on loans allowed for completion of Upper Indravati and Potteru
Hydro Electric Project would further aggravate the situation
by substantially raising the revenue requirement for the
licensees to meet the extra burden of interest costs. As
disclosed from the revenue trend of last five years even
without the impact of the servicing of those bonds, the
licensees were neck deep in meeting their financial obligations
and accretion of those new liabilities would add to the
further woes of the sector. |
| 6.2.23 |
With this scenario in
view, the committee of independent experts (hereafter called
the Kanungo Committee) appointed by the Government of Orissa
have very aptly recommended, as a mid-course correction,
certain measures setting aside the revaluation assets of
OHPC, payment of interest to the State Government on the
loans imposed on the licensees due to revaluation to provide
requisite support to the power sector for its resuscitation
and among other things have made the following significant
recommendations :
- Revaluation of GRIDCO and OHPC assets
to be kept in abeyance till the system is brought to
balance.
- State Government to agree to allow
moratorium on debt servicing to the State except the
amounts in respect of loans from the World Bank.
- An interim financial package amounting
to Rs.3240 Crore (estimated) to be availed from World
Bank and the DFID to bridge the cash gap in order to
keep the tariff at the same level for the period from
2001-02 to 2004-05.
- Instituting regular systems of monitoring
of consumer grievances and services supplemented by
test checks.
- Setting up of Rural Engineering Planning
Organisation (REPO) and Rural Electrification Planning
Units (REPU) under Government of Orissa to monitor RE
and LI works.
- At this point of crisis, all agencies
such as State Government, the Central Government, the
World Bank and DFID should get together to rescue the
reform process.
- Reduction of distribution loss @ 5%
p.a. with a base level of 42.2% in the year 2001-02.
- Collection efficiency of DISTCOs to
increase from 76% to 85% by 2004-05.
|
| 6.2.24 |
The inescapable conclusion
emerges from the aforesaid observation is that support for
sectoral revival can be possible with reduction in input
cost to the distribution companies, which has occurred on
account of exponential rise in (a) cost of power (b) cost
of transmission (c) cost of distribution. The rise in power
purchase cost has been more steep in respect of Orissa Hydro
Power Corporation (old stations) where the per unit cost
of power purchase went up from 22 paise/unit as on 31 March,
1996 to 38 paise/unit as on 1 April, 1996 and49 paise/unit
between 1997-98 to 2000-01. GRIDCO has proposed to raise
the cost of OHPC power to 72 paise/unit with effect from
1 April, 2001 as a result of expiry of the period of moratorium
on Government loans. |
| 6.3 |
Strategies for Improvement
of Power Sector |
| 6.3.1 |
Against this backdrop,
the Commission deems it fit to have a review of the various
policy options being followed in the post reform era in
the best interest of the power sector in the state within
the frame work of existing Act, Rules and Regulations. In
fact, Commission in its tariff order and conceptual paper
of August, 1998 had reserved the right to review those points
at an appropriate time. |
| 6.3.2 |
In course of the hearings,
the utilities as well as some of the respondents spoke about
the element of uncertainty and risk inherent in an annual
tariff setting exercise and they pleaded for introduction
of a multi-year tariff regime which would reduce such uncertainty.
The Commission is conscious of the need for greater certainty
in the regulatory treatment of a host of issues having direct
impact on tariff setting. The Commission shall endeavour
to set in motion a multi-year tariff principle regime effective
from April, 2003 for FY 2003-04 after wide publicity and
consultation with all the stakeholders. The Commission initiated
preparation of a five-year sectoral plan covering generation,
transmission and distribution which will provide key inputs
to this exercise. The draft consultation document which
is currently under finalisation will also be brought out
to facilitate the process of such consultation and obtain
comments from the various stakeholder. |
| 6.3.3 |
The utilities have to
improve upon their own performance within a stipulated time
frame by upgrading their managerial skills and efficiency
by scrupulously adhering to certain operational norms like
reduction in the level of loss, attaining certain level
of billing and collection efficiency, setting a target for
investment and avoiding time and cost overrun in execution
of projects, etc. This calls for not a single year target
but fixing a target to be achieved over a control period
to provide a kind of predictability to the consumers and
to their own shareholders and to the Commission. The Commission
considers it prudent and desirable to go for a multi-year
tariff principle regime for which the utilities should conform
themselves to a multi-year target setting in the areas stated
above. The Commission also feel that the FY 2001-02 should
be considered as the base year for all calculations as suggested
by the Kanungo Committee. |
| 6.3.4 |
It is also felt at this
stage that steep hike in tariff would not be implementable.
A reasonable level of tariff rise that prescribes a competitive
tariff for the industrial and commercial enterprises coupled
with rationalization of the tariff structure can help in
growth of these categories. This calls for support to the
transmission and distribution utility in the form of reduced
cost input in the power purchase which can help in bringing
about sectoral revival including improvement in quality
of supply and service to the customer. |
| 6.3.5 |
The options available
are :-
- Suggest and adopt means for neutralization
of the effect of asset revaluation
- For improvement of the liquidity of
the licensee to examine the issue of securitisation
of power purchase liability of GRIDCO in respect of
long term bonds in consonance with the recommendations
of Ahluwalia Committee.
- direct the utilities to commit to definite
and unambiguous target like reduction of transmission
and distribution loss in a time bound period.
- confirmation from the utilities for
achieving certain minimum level of collection and billing
from year to year.
- direct the utilities to bring in working
capital to take up required repair and maintenance work.
- determination of revenue requirement
based on the level of transmission and distribution
loss, level of billing in collection in accordance with
the parameters stated above.
|
| 6.3.6 |
The Commission considers
the necessity of certain short-term measures for immediate
implementation to reduce the revenue requirement of the
utilities to contain the tariff rise at a reasonable level
without affecting the financial viability of the Generators,
GRIDCO and DISTCOs. The Commission, therefore, first would
like to analyse the impact of revaluation of assets and
explore means of neutralising its adverse effect in increasing
the revenue requirement of the utilities. |
| 6.3.7 |
It is an undisputed
fact that the revaluation of assets of OHPC/GRIDCO has substantially
raised cost of power from OHPC which in turn resulted in
enhancement of GRIDCO's cost of power procurement and the
revenue requirement of the transmission and distribution
business of GRIDCO and DISTCOs. At para 8.4 of order No.009
dt.12.03.1997 in case No.4 of 1997, revaluation of asset
was dealt which is quoted below :-
"Objections with regard
to reform, restructuring and steps for privatisation programme,
and various facets of transfer scheme, revaluation of assets,
etc. are beyond the scope of this Commission as these have
been done either in consequence or through an Act of the
legislature of which the Commission is a creature."
|
| 6.3.8 |
The Commission being
acutely aware of the adverse impact of upvaluation had dealt
the issue in the conceptual paper for tariff setting. Asset
valuation and its treatment as per Conceptual Issues of
Electricity Tariff issued by OERC in August, 1998 in consultation
with GRIDCO and with economists, industry association, power
professionals and consumer groups are reproduced as below
:-
"If the overall revenue requirements are to be set using
accounting costs, then what measure of plant value should
be included in the rate base component used in the determination." |
| 6.3.9 |
There are four possible
measures of plant value for the calculation of the rate
base viz. original cost less depreciation, reproduction
or replacement cost less depreciation, the value assigned
by the Government when it was transferred to GRIDCO and
the certified values being produced by GRIDCO for privatization
under the Companies Act. The Commission first encountered
this issue in the last GRIDCO tariff proceeding when it
had faced with a decision on whether to value GRIDCO's investment
in plant at the original cost at the time the property was
put in service or at the value assigned to the investment
by the Government when it was transferred to GRIDCO. As
new values are being developed for the four distribution
entities, this issue will surely come up again as potential
purchasers of the GRIDCO system consider the level of their
offers. |
| 6.3.10 |
While arguments can
be made for the use of other measures of plant value for
rate base, the Commission has no choice but to accept the
plant values certified by Government for GRIDCO at the time
of transfer of assets plus any prudent capital additions
made by the licensees at original cost less depreciation.
The value set by Government under the scheme to transfer
assets from the erstwhile OSEB to GRIDCO formed the basis
of the calculations in the last consideration and the Commission
will continue to use the transfer value until it is demonstrated
before it that regulatory principles or public interest
requires a change to be made. Such changes will not be made
lightly as the Commission places substantial weight on the
principle of predictable and stable tariffs and tariff methods.
|
| 6.3.11 |
While GRIDCO agrees
with the Commission that the total value of the zonal assets
should not exceed the total value of the distribution assets
as set out in the Transfer Scheme as adjusted for subsequent
additions and depreciation, it may be worthwhile to use
the revalued fair price of the assets to avail of short-
and long-term loan from financial institutions. The latter
will enhance creditworthiness of the licensee while tariff
will be based on depreciated book value as set out in the
Transfer scheme adjusted for subsequent addition & depreciation."
|
| 6.3.12 |
In accordance with the
policy guidelines set out in the conceptual issues, the
Commission used the transfer values for the purpose of determination
of tariff till 2000-01. But as stated earlier, the following
projections as per SAR (Staff Appraisal Report) of the World
Bank did not materialize viz.
- Projected load growth
- Reduction of transmission and distribution
loss
- Efficiency in billing and collection
|
| 6.3.13 |
The Commission makes
it abundantly clear that it proposes not to disturb the
revaluation of the asset, which definitely enhances the
creditworthiness of the licensee including the privatised
distribution utilities. But the Commission has also to place
substantial weight on the principle of predictable and stable
tariff affordable by the consumers. It has, therefore, become
imperative in the public interest to keep in abeyance the
effect of the revaluation for the purpose of determination
of tariff until the sector turns around. |
| 6.3.14 |
Hence the Commission in
exercise of its power under Section 11 of the OER Act, 1995
advises the Government to take necessary actions to make
suitable amendment to the transfer notification issued by
the Dept. of Energy, Government of Orissa order dt.1.4.96
as mentioned in para 6.3 (a) and (b) so as to provide necessary
support for the success of the power sector reform in Orissa.
|
| 6.4 |
Depreciation of Distcos |
| 6.4.1 |
Government of India,
Ministry of Power in their letter dt.01.6.99 addressed to
the CMD, OHPC stated that the rates of depreciation as notified
by the Central Government can only be a guiding factor and
not be a binding factor on the Regulatory Commission. If
the circumstance warrant CERC or SERC may, for the purpose
of determination of tariff allow a different rate of depreciation.
However, they will have to justify the same with reasons.
|
| 6.4.2 |
Further, it was clarified
in the said letter that the power to determine the tariff
includes the power to apply rate on depreciation and other
concepts such as reasonable return. When Section 43A sub-section
2 is deleted, it will not be assumed that the Central Government
looses power to fix depreciation principles for SEBs. It
merely means that Central Government will have no authority
to fix depreciation for the generating company selling power
in SEB for the State. |
| 6.4.3 |
As stated earlier, the
objective of revaluation for GRIDCO that also included the
distribution business was to help the sector to provide
more self-financing for new investment with higher depreciation,
which the owner could recover through tariff. The provisions
of the Sixth Schedule of the Supply Act, 1948 para VI(a)
states "The licensee shall provide each year for depreciation
such sum calculated in accordance with the principles as
the Central Government may, after consultation with the
Authority, by notification in the Official Gazette, lay
down from time to time". |
| 6.4.4 |
In the instant case,
depreciation is being calculated at post'94 rate as prescribed
by the Government of India on the asset base that was revalued
on 01.4.96 which has substantially raised the revenue requirement
of the transmission and distribution business. The Government
of India notification on depreciation issued in pre-1992
links the rate of depreciation to the age of the asset.
The Commission in the public interest decides that the licensees
will be allowed to recover 90% of the asset value within
the life period of the asset as determined in the Government
of India notification of 1992. This will avoid front loading
of the tariff, but at the same time will ensure necessary
cash flow for the licensee over a longer period of time.
Accordingly, the Commission directs that the depreciation
of the assets should be limited to 90% of the revalued cost
of the assets. The depreciation should be calculated from
01.04.2001 onwards after taking into account the extent
of higher depreciation already recovered during 01.04.1996
to 31.3.2001 at pre-92 rate. |
| 6.4.5 |
Securitisation of Power
Purchase dues :In OERC Order No. Case No.29 & 30/2000
dtd.16.03.2001 on FRP and securitisation, the Commission
observed in the concluding remarks "the Commission grants
in principle approval of the Financial Restructuring Plan
indicated in paras 12 and 13 of this order and plan for
rescheduling of loans as contained in their application
dtd.19.09.2000 vide Case No.30/2000 dtd.30.09.2000 and 29/2000
dtd.19.09.2000 respectively. GRIDCO with the support of
GOO must plead with the GOI and the funding agencies for
one time settlement, waiver of dues and fresh loans and
after taking the results into account, implement the financial
restructuring plan to revise GRIDCO so as to put it on recovery
path towards viability". |
| 6.4.6 |
Further, the Commission
has observed, "the retail tariff levels as proposed in the
FRP is based on the BST calculation. The projection has
not taken into account the debt service due to the tax free
bonds to be issued by GRIDCO. On the other hand they have
proposed additional borrowing to the tune of Rs.929 Crore
in the year 2001 and further Rs.631 Crore in the year 2002.
This will definitely impact the BST as well as the retail
tariff thus upsetting some of the crucial FRP assumptions.
We are not in a position to give clearance and commitment
for future tariff, as these will be dealt separately on
a year to year basis in accordance to the OER Act". |
| 6.4.7 |
A submission was made
on behalf of GRIDCO during the course of the public hearing
that GRIDCO has not been able to pay the dues to generators
due to non-payment by the DISTCOs to GRIDCO. The power purchase
payables as on 28 of February 2001 is given below :
Table : 5
(Rs. in Crore)
|
Power Purchase Payables
(As on 28th Feb,2001 without March,01 bill)
|
|
Central Sector Generators
|
Principal outstanding
|
DPS outstanding
|
40% DPS applicable for
securitisation
|
Total outstanding for
securitisation
|
|
NTPC (Incl. TTPS)
|
410.73
|
126.75
|
50.70
|
461.43
|
|
NHPC
|
5.05
|
9.87
|
3.95
|
9.00
|
|
PGCIL
|
11.39
|
-
|
|
11.39
|
|
NALCO
|
156.46
|
-
|
|
156.46
|
|
Total CPSUs payables
|
583.63
|
136.62
|
54.65
|
638.28
|
|
| 6.4.8 |
GRIDCO pleaded that
NTPC has been regulating power supply to Orissa due to non-payment
of dues and in accordance with the CERC order dt.11 January
2002 a utility will be required to bear the fixed cost of
the generators in proportion to the share allocation during
the period of energy regulation by the central generators.
In this situation, the liability of GRIDCO will further
increase if the Commission does not reconsider its own decision
of not allowing the interests on account of securitization
of power purchase liabilities. In view of the regulation
of power by NTPC, it has become extremely urgent on the
part of GRIDCO to create special purpose vehicle for securitizing
power purchase liability of NTPC through issue of bonds
and the Commission may permit the interest on bond as a
pass through in the revenue requirement for the year 2001-02
and 2002-03. As indicated in para above, 6.4.5 the Commission
being concerned about the mounting liabilities of GRIDCO
accepts securitisation of current liabilities as on 28.2.2001
payable to CPSUs like NTPC and NALCO through issue of new
bonds. In addition to this, the Commission also accepts
the interest liability of the past bonds issued by GRIDCO
which was earlier disallowed provided these bonds are converted
in line with recommendation of Ahluwalia Committee. |
| 6.4.9 |
The financial position
of GRIDCO is such that the liability on account of power
purchase is on the rise as already indicated earlier due
to non-payment of BST bills by the distribution companies
creating a debt trap both for GRIDCO as well as for the
generators. At the time of passing of the FRP order indicated
in para 6.4.5 above the issue of pass through of the burden
of interest on power bonds on account of non-payment of
power dues is required to be addressed in this tariff order.
The Commission has come to a conscious decision that unless
the power purchase liabilities are allowed to be securitised
in full, the problem of liquidity cannot be addressed. In
any case, this has to be a one time settlement in accordance
with the policy followed at the national level where the
GOI has very categorically accepted the ground realities
and allowed securitisation of power dues as well as other
dues payable to the GOI organisations by the SEBs. The case
of Orissa is no different except that it has taken an advance
step of reforming its own power sector for which SEB has
been replaced by the GRIDCO and the DISTCOs. Accordingly,
this principle should be applicable mutatis mutandis to
GRIDCO which is purchasing bulk power from generators. |
| 6.4.10 |
This will have the advantage
of retiring high cost debts carrying surcharge as high as
24% per annum, (LPSC @ 2% p.m.) for the central generators.
Securitisation of these dues will reduce the interest burden
to 8.5% as recommended by the Ahluwalia Committee in its
report for one time settlement for CPSU dues and accepted
by the Government of India. The Commission would further
expect that the dues of CPSUs like NALCO should also be
securitised by GRIDCO in a similar manner. |
| 6.4.11 |
As far as the recovery
of interest from DISTCOs is concerned, the analogy as applied
for GRIDCO shall apply in this case, since there is a back
to back arrangement between GRIDCO and DISTCOs for recovery
of the institutional loans handed over at the time of separation
of distribution business from GRIDCO. Interest shall be
calculated during the year 2002-03 on the loans and pass
bonds securitized carrying a lower rate of interest of 8.5%.
|