| 4.0
|
OBJECTIONS
DURING HEARING
The Commission admitted twenty objections against Retail
Supply Tariff application, 2001-02 and four objections against
the Revenue Requirement application, 2002-03 for personal
hearing. Some of the objections were of general nature and
others were specific to the tariff filing of 2001-02 and
Revenue Requirement of the licensee for 2002-03. Summary
of these objections based on issues raised are presented
below: |
| 4.1 |
The Commission considered
the objection raised by the various objectors. Based on
their nature and type, these objections may be categorised
broadly as under:- |
| 4.2 |
Period of implementation of the tariff |
| 4.2.1 |
Some of the objectors
suggested that tariff revision proposed for the year 2001-02
and revenue requirement for 2002-03 should be taken up together. |
| 4.2.2 |
It was also pointed out
by some of the objector that recommendation of the "Report
of Committee on Power Sector Reform" in Orissa, October,
2001 should be decided first by State Government before
making any decision on tariff revision proposal by the Commission. |
| 4.2.3 |
Some of objectors also
pointed out that tariff shall not be fixed or amended in
quick succession as it is not tenable under law and opposed
to OER Act. Tariff shall not be amended within a period
of three years. |
| 4.2.4 |
For an industry, long term tariff for a reasonable
period of 5 years be fixed. |
| 4.3 |
Audited Accounts
Some of the objectors have stated the following on audited accounts:- |
| 4.3.1 |
Licensee's account has
not been audited and account are not maintained properly. |
| 4.3.2 |
The latest audited accounts
for the year upto March, 2001 have not been furnished. |
| 4.3.3 |
WESCO has not submitted the latest Audit report. |
| 4.4 |
Transmission and Distribution Loss |
| 4.4.1 |
Majority of the objectors
strongly objected to high T&D loss assumed by WESCO
and gave the following comments:- |
| 4.4.1.1 |
In absence of adequate
metering installation, applicant is overstating the distribution
loss figure to claim higher requirement and consequent increase
on tariff. |
| 4.4.1.2 |
Number of unmetered consumers
has increased much and reduction of consumers with defective
meters is negligible. |
| 4.4.1.3 |
No studies were conducted
to asses the actual losses nor suitable meter installed
at 11 KV & LT to measure technical loss. |
| 4.4.1.4 |
Distribution loss projected
by WESCO is 43% in 2000-01 and 38% in 2001-02, whereas actual
loss on Rajgangpur, Rourkela 33 KV feeder is 3% only. |
| 4.4.1.5 |
WESCO is not consistent
in projecting its distribution losses and has never been
able to meet its targeted loss. |
| 4.4.1.6 |
WESCO has conducted energy
audit and loss audit of Bargarh pision where the total
loss is 58.5% to 65.48% out of which technical loss has
been shown 13.98% to 14.43%. |
| 4.4.1.7 |
Some objectors suggested
the following measures for reduction of T&D loss.
- WESCO should give priority
for supply of meters and replacement of defective meters.
- Sub contracting through village Committee/other agencies
may be introduced for the purpose of domestic collection
and billing to minimise commercial losses and improving
collection.
- Tariff rationalisation, load factor incentive should be
introduced to minimise commercial loss.
- Effective maintenance of transformer, jumper, conductor.
|
| 4.5 |
Employees Cost,
Material Cost and A& G Expenses
Many objectors have pointed out that the cost of employees,
material cost, A&G expenses are quite high and should
be increased 6% over Commission's approved figure of 2000-01 |
| 4.6 |
Collection efficiency
and provision for bad and doubtful debt
Regarding collection efficiency some of the objectors have
pointed out that collection efficiency of WESCO in LT is
only 45% and the projected increase in bad debt manifests
its non-accountability and poor collection. The collection
efficiency of WESCO should be minimum 90%. Some objectors
stated that collection made out of huge outstanding arrears
which is presently 5.40 months of sale are not shown. Shri
R.P. Mohapatra specifically raised during public hearing
that list of debts written off is not available nor the
arrears have been deleted from the ledger. He pointed out
that arrear revenue relating to pre privatisation period
collected by the licensee is not shown as revenue, nor 50%
of arrear collection is given to GRIDCO, which is their
legitimate revenue. Therefore Commission should only make
a token provision of bad debt. Allowing 15% of incremental
arrears as bad debt is a premium for inefficiency. Mr. G.
Pujari representing Sundargarh Dist. Employees Association
stated that Bad debt may be permitted to the extent of 1%
on HT and 5% on LT sales. |
| 4.7 |
Depreciation
Objectors like Shri R.P. Mohapatra, Shri Kulamani Acharya
and Shri G. Pujari suggested modification in calculation
of depreciation. Shri R.P. Mohapatra suggested that rate
of depreciation based on MoP, GoI notification of 1994 are
meant for assets purchased new. It is thus applicable to
assets purchased on or after 01.04.1994. Rate of depreciation
on other assets is to be determined by Government, Commission
may allow depreciation for assets created before 3/94 at
old rates pending revised notification by GoO.
Shri Acharya has stated
that pre-1992 rate of depreciation should be applied.
Shri Pujari has stated to calculate depreciation on original
cost of asset and not on revalued cost.
|
| 4.8 |
Rationalisation
of Tariff
Many objectors suggested the following for rationalisation
of tariff :-
- Increased consumption by consumers should be rewarded
and present restriction on special tariff on 100 MVA with
80% load factor should be rationalised and the same should
be available to HT and EHT consumers having contract demand
of 300 KVA and above.
- Present restriction on special tariff for 50 MVA to be
reviewed. The same should be available to HT, EHT consumers
having a contract demand of 200 KVA.
- Existing provision of load factor incentive and over drawal
penalty should be reviewed.
- Maintaining power factor above 97% is rare. This needs
revision. Power factor incentive may be allowed starting
from 90% PLF as was allowed in the earlier tariff orders.
- Tariff for commercial consumers of LT category should
be reduced.
- Proposal to increase colony consumption from Rs.2.30 per
unit to Rs.2.60 per unit is highly unjustified. For colony
consumption ceiling limit of 10% of total units consumed
should be waived and the rate applicable to domestic consumer
should be applicable.
- Allowing prompt payment rebate within 48 hours of payment
of the bill is arbitrary.
|
| 4.9 |
Cross Subsidy
Some of the objectors stated that EHT, HT consumers are
charged more than cost of energy. Therefore cross subsidy
should be reduced and their tariff should be considered
for reasonable reduction. Objectors proposed the following
measures for reduction in cross subsidy.
- Government of Orissa may reimburse electricity
duty to fund part of subsidy
- Irrigation and Kutirjyoti subsidy should
be funded by State Government
- Substantial growth in HT and EHT consumes
may be planned so that more subsidies available to low voltage
class of consumers.
- WESCO has to improve its efficiency
by reducing Distribution loss. |
| 4.10
|
Calculation of
Reasonable Return and Capital Base
Some of the objectors have pointed out that for the purpose
of calculation of capital base "Original Cost of Fixed Asset"
is to be taken in to consideration. Capital base should
be taken from audited balance sheet. Regarding reasonable
return objectors suggested that inefficient, loss making
company with negative capital base should not be permitted
reasonable return. |
| 4.11 |
Provision of
previous loss shown in special appropriation
WESCO's proposal on showing the previous loss as special
appropriation is objected by some of the objectors. They
stated that provision of previous losses should not be included
in tariff. |
| 4.12 |
Interest
M/s. INDAL and UCCI, Cuttack have stated that WESCO's claim
for Power Bond interest should not be allowed as consumers
are not responsible for non-payment of energy bills to DISTCOs.
Some of the objectors stated that WESCO should arrange working
capital fund from bank to reduce interest burden and avoid
paying DPS. |
| 4.13 |
Interruption, Low Voltage
and Unreliable Supply
Due to poor maintenance of feeders there are frequent power
failures for which production in industry is seriously affected.
Therefore quality of power should be improved. |
| 4.14 |
Clarification
from WESCO by DIRECTOR (TARIFF)
During hearing Director(Tariff), OERC sought certain clarification
from WESCO on following issues : |
| 4.14.1 |
In the RR application
T&D loss proposed for the year 2002-03 is 41.09% whereas
for the same year it is shown as 39% in the business plan.
Similarly for 2001-02 in the tariff application T&D
loss is proposed at 38.01%. But in the business plan it
is shown at 41.08%. Reason for the discrepancy may be provided. |
| 4.14.2 |
In the RST proposal for
2001-02 the distribution loss is shown at 38.01% whereas
the same for the year 2001-02 in the ARR application of
2002-03 is shown at 45.06%. This may be clarified. |
| 4.14.3 |
Details of loss reduction programme (Form
P-14) may be furnished. |
| 4.14.4 |
Under the head "interest
on working capital" a sum of Rs.21.73 crore for the FY 2001-02
and a sum of Rs.48.50 crore for the FY 2002-03 is shown
for payment of DPS to GRIDCO. WESCO may clarify why this
DPS should be allowed for recovery through tariff when it
estimates receivables at Rs.511.29 crore as on 31.03.2002
and Rs.631.41 crore as on 31.03.2003. |
| 4.14.5 |
WESCO has proposed Rs.1.28
crore for the financial year 2001-02 and Rs.1.00 crore for
the FY 2002-03 towards organisational development mainly
to be spent for microprivatisation. The cost benefit analysis
of this investment may be given. |
| 4.14.6 |
For the FY 1999-00 miscellaneous
receipt was Rs.4.36 crore but in spite of installation of
large number of meters, WESCO has shown a lower figure of
miscellaneous receipt towards meter rent as Rs.3.27 crore
in 2001-02 and Rs.3.80 crore in 2002-03. Lower projection
of miscellaneous receipt may be clarified. |